Every month, EIA's survey of planned generators (EIA-860M) lists each project's status (planned, approvals pending, approved, under construction, more than half built) and the month it expects to start. Earlier results showed that projects further along, and projects due sooner, are more often online by the planned month. This post asks whether those are two facts or one. It scores every planned month 0-24 months ahead in the reports from January 2016 to June 2023 (87,351 rows over 6,483 generat...